SOLAR ROOFTOP POWER PLANT INAUGURATION 2026

Date: 23 January 2026
Venue: HT Power House

The HT Power House proudly inaugurated a 990 kW Solar Rooftop Power Plant on 23rd January 2026, marking a major milestone in renewable energy adoption. This installation stands as Dakshina Kannada’s largest rooftop solar power plant and the Mangaluru Division’s first solar project utilizing a non-penetration mounting system.

The plant is installed using advanced non-penetration mounting technology, where the entire structure is securely fixed using high-strength industrial adhesive, ensuring zero drilling and no roof penetration, thereby preserving the structural integrity of the rooftop.

The system is equipped with German-made LUXRA SOLARKAUF glass-to-glass solar panels, each rated at 600 Wp, known for their high efficiency, durability, and long operational life.

The solar rooftop plant generates approximately 120,000 units of clean energy per month and contributes to a significant CO₂ reduction of about 1,200–1,500 metric tons per year, reinforcing the institution’s strong commitment to sustainability and green energy initiatives.

Inauguration Ceremony

The inauguration ceremony was presided over by:

  • Dr. K. V. Chidananda, Medical Director, KVG Medical College & Hospital
    & President, Academy of Liberal Education (AOLE)
  • Mrs. Shobha Chidananda, Vice President, AOLE

The occasion was graced by several eminent personalities associated with KVG Medical College & Hospital and AOLE, including:

  • Dr. Neelambikai Natarajan, Dean, KVGMC&H
  • Dr. C. Ramachandra Bhat, Medical Superintendent
  • Dr. Aishwarya K. C., Director, KVG Medical College & Hospital & Secretary, AOLE
  • Ar. Akshay K. C., Executive Director, KVGMCH & General Secretary, AOLE

All dignitaries conveyed their best wishes and appreciated the institution’s proactive initiative towards renewable energy and environmental responsibility. The event was also attended by faculty and staff of KVG.

Project Execution

The project was successfully executed and installed by M/s Helios Solar, Bangalore, and formally inaugurated on 23rd January 2026.

Highlights of the Project

  • Installed Capacity: 990 kW
  • Solar Panels: German LUXRA SOLARKAUF glass-to-glass panels (600 Wp each)
  • Monthly Energy Generation: ~120,000 units
  • CO₂ Reduction: 1,200–1,500+ metric tons annually
  • Coal Reduction Equivalent: ~750–850+ tons
  • Annual Tree Plantation Equivalent: 22,000–38,000+ trees
  • Mounting Technology: Non-penetration (no drilling, no roof damage)

Dean

Dr. Neelambikai Natarajan

Dr. Neelambikai Natarajan is a alumna of Thanjavur Medical College, where she obtained her medical degree. She further pursued her MD in Physiology from Madras Medical College and an MBA in Hospital Administration from Alagappa University.

Throughout her academic medical career, Dr. Natarajan has served in various capacities at several prominent institutions, including Madras Medical College, Madurai Medical College, Government Medical College Coimbatore, Government KAP Vishwanathan Medical College in Trichy, and Meenakshi Medical College in Kanchipuram. With over 20 years of administrative experience, she has held the position of Dean in multiple medical colleges for more than a decade. Her expertise in faculty training within medical education has earned her widespread recognition.

In addition to her administrative roles, Dr. Natarajan has served as an assessor on the Medical Council of India (MCI) panel for over 15 years. She was also an Ex-Senate member of the MGR University and Secretary of the Ethics Committee. Dr. Natarajan has completed an Advanced Course in Medical Education (ACME). Since 2019, she has been serving as the Dean at KVG Medical College and Hospital in Sullia.